OmniPlan Report for Project DVP 1

ID Task Start End Duration Completed Dependencies Task Cost Assigned Planned Start Start Variance Constraint Start Planned End End Variance Constraint End
0 DVP 1 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
1 Delta Visioning Process 8/3/06 8:00 AM 5/23/07 5:00 PM 42w 0% Blue Ribbon Task Force, Cabinet Secretaries, DVP Core Team
2 Project Administration 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
2.1 Select DVP Core Team Team members and consultants 8/3/06 6:15 PM 8/15/06 5:00 PM 1w 3d 0% Cabinet Secretaries
2.2 Identify and request staff from Cabinet agencies 9/1/06 6:15 PM 9/29/06 5:00 PM 4w 0% Cabinet Secretaries
2.3 Select DVP Project Manager 8/3/06 6:15 PM 9/15/06 5:00 PM 6w 1d 0%
2.4 Prepare budget and schedule 8/7/06 10:10 AM 3/15/07 3:30 PM 31w 3d 4.25h 0%
2.4.1 Calibrate budget and schedule to critical path activities 8/7/06 10:10 AM 9/4/06 9:05 AM 3w 4d 7h 0% Kamyar, Elizabeth
2.4.2 Periodically revise budget and schedule as necessary 1/2/07 3:30 PM 3/15/07 3:30 PM 10w 2d 0% Elizabeth
2.5 IT Coordination and DVP Web Portal 8/3/06 6:15 PM 12/31/08 5:00 PM 125w 4d 0% John
2.6 Establish and maintain documents retention 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
2.6.1 Establish document retention policy and procedures 9/15/06 8:00 AM 10/4/06 2:20 PM 2w 3d 5.25h 0% John, Nancy, Greg
2.6.2 Select method and place where documents will be maintained 9/20/06 8:00 AM 9/27/06 5:00 PM 1w 1d 0%
2.6.3 Maintain archiavel system 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
2.7 Legislative and Executive Roles 8/3/06 8:00 AM 10/17/07 5:00 PM 63w 0%
2.7.1 The designated Cabinet Secretaries (Resources, BTH, DFA and Cal EPA) will work with key members of Legislature (particuarly from the Delta-Suisun) to assist with the DVP 8/3/06 8:00 AM 10/17/07 5:00 PM 63w 0% Cabinet Secretaries, Blue Ribbon Task Force
3 Convenethe Blue Ribbon Task Force 8/3/06 8:00 AM 12/16/08 5:00 PM 123w 4d 0%
3.1 Select chair and panelists 8/3/06 8:00 AM 9/15/06 5:00 PM 6w 2d 0% Cabinet Secretaries
3.2 Determine the number of workshops 8/14/06 8:00 AM 8/15/06 12:00 PM 1d 4h 0% Kamyar, Blue Ribbon Task Force
3.3 Panel reviews Delta Vision Report using agreed upon review protocols 6/3/07 8:00 AM 1/4/08 5:00 PM 31w 0% Blue Ribbon Task Force
3.4 Deliver the final DV Report 1/5/08 8:00 AM 6/16/08 5:00 PM 23w 1d 0% Blue Ribbon Task Force
3.5 Deliver the final Delta Strategic Plan 6/16/08 8:00 AM 12/16/08 5:00 PM 26w 2d 0% Blue Ribbon Task Force
4 Communications 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
4.1 Develop Communications strategy for DVP 9/4/06 8:00 AM 10/17/06 5:00 PM 6w 2d 0%
4.1.1 Identify exisitng communication efforts that DVP can use to spread its message 9/15/06 8:00 AM 10/17/06 5:00 PM 4w 3d 0%
4.1.2 Identify new communication efforts specific to DVP 9/15/06 8:00 AM 10/13/06 5:00 PM 4w 1d 0%
4.2 Editorial Review and Coordination 10/3/06 8:00 AM 12/1/06 5:00 PM 8w 4d 0%
4.2.1 Establish an Executive Editorial Review Panel 10/15/06 8:00 AM 11/15/06 5:00 PM 4w 3d 0%
4.2.1.1 Determine membership and meeting structure 10/16/06 8:00 AM 11/15/06 5:00 PM 4w 3d 0%
4.2.2 Establish writing team 10/3/06 8:00 AM 10/3/06 5:00 PM 1d 0%
4.2.2.1 Identify and recruit techinical or research writers, PIOs and graphic atists to be on the team 10/3/06 8:00 AM 10/3/06 5:00 PM 1d 0%
4.2.3 Develop editorial guides to assist principal authors of DVP reports, etc. 11/1/06 8:00 AM 12/1/06 5:00 PM 4w 3d 0%
4.3 Brochures, newsletters, and printed material other than reports or speeches 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
4.3.1 Based on DVP communication strategy, write and produce necessary information 8/3/06 8:00 AM 12/31/08 5:00 PM 126w 0%
4.4 Coordinate media relations with Delta-Suisun state planning efforts 9/1/06 8:00 AM 12/12/08 5:00 PM 119w 1d 0%
4.4.1 Develop PIO team 9/5/06 8:00 AM 9/15/06 5:00 PM 1w 4d 0%
4.4.2 Develop master list and calendar of PIOs and media events 9/1/06 8:00 AM 12/12/08 5:00 PM 119w 1d 0%
4.5 Coordinate stakeholder outreach 8/3/06 8:00 AM 12/15/08 5:00 PM 123w 3d 0%
4.5.1 Develop speakers bureau (or similar sort of outreach program 1/3/07 8:00 AM 3/15/07 5:00 PM 10w 2d 0%
4.5.2 Coordinate with WEF and CCP in tracking stakeholder concerns 8/3/06 8:00 AM 12/15/08 5:00 PM 123w 3d 0%