OmniPlan Resource Report

Project: DVP 1

Name Start Date End Date Duration Task Cost
Elizabeth 8/7/06 10:10 AM    14w 1d 7h
    Calibrate budget and schedule to critical path activities 8/7/06 10:10 AM 9/4/06 9:05 AM 3w 4d 7h
    Periodically revise budget and schedule as necessary 1/2/07 3:30 PM 3/15/07 3:30 PM 10w 2d
Sergio      
Nancy 9/15/06 8:00 AM    2w 3d 5.25h
    Establish document retention policy and procedures 9/15/06 8:00 AM 10/4/06 2:20 PM 2w 3d 5.25h
Darcy      
John 8/3/06 6:15 PM    128w 2d 5.25h
    IT Coordination and DVP Web Portal 8/3/06 6:15 PM 12/31/08 5:00 PM 125w 4d
    Establish document retention policy and procedures 9/15/06 8:00 AM 10/4/06 2:20 PM 2w 3d 5.25h
Kamyar 8/7/06 10:10 AM    4w 1d 3h
    Calibrate budget and schedule to critical path activities 8/7/06 10:10 AM 9/4/06 9:05 AM 3w 4d 7h
    Determine the number of workshops 8/14/06 8:00 AM 8/15/06 12:00 PM 1d 4h
Greg 9/15/06 8:00 AM    2w 3d 5.25h
    Establish document retention policy and procedures 9/15/06 8:00 AM 10/4/06 2:20 PM 2w 3d 5.25h
Ralph      
DRMS Report      
DRERIP Report      
Status and Trends Report      
Computer Server      
Blue Ribbon Task Force 8/3/06 8:00 AM    185w 4d 4h
    Delta Visioning Process 8/3/06 8:00 AM 5/23/07 5:00 PM 42w
    The designated Cabinet Secretaries (Resources, BTH, DFA and Cal EPA) will work with key members of Legislature (particuarly from the Delta-Suisun) to assist with the DVP 8/3/06 8:00 AM 10/17/07 5:00 PM 63w
    Determine the number of workshops 8/14/06 8:00 AM 8/15/06 12:00 PM 1d 4h
    Panel reviews Delta Vision Report using agreed upon review protocols 6/3/07 8:00 AM 1/4/08 5:00 PM 31w
    Deliver the final DV Report 1/5/08 8:00 AM 6/16/08 5:00 PM 23w 1d
    Deliver the final Delta Strategic Plan 6/16/08 8:00 AM 12/16/08 5:00 PM 26w 2d
member 1      
member 2      
member 3      
chair      
Cabinet Secretaries 8/3/06 8:00 AM    117w
    Delta Visioning Process 8/3/06 8:00 AM 5/23/07 5:00 PM 42w
    Select DVP Core Team Team members and consultants 8/3/06 6:15 PM 8/15/06 5:00 PM 1w 3d
    Identify and request staff from Cabinet agencies 9/1/06 6:15 PM 9/29/06 5:00 PM 4w
    The designated Cabinet Secretaries (Resources, BTH, DFA and Cal EPA) will work with key members of Legislature (particuarly from the Delta-Suisun) to assist with the DVP 8/3/06 8:00 AM 10/17/07 5:00 PM 63w
    Select chair and panelists 8/3/06 8:00 AM 9/15/06 5:00 PM 6w 2d
Resources      
CalEPA      
DFA      
BTH      
DVP Core Team 8/3/06 8:00 AM    42w
    Delta Visioning Process 8/3/06 8:00 AM 5/23/07 5:00 PM 42w